| Activity |
Timeline |
Who |
| Professional development (PD) and technical assistance (TA) for wave 1 schools |
July-August 2011 |
DPI |
| Implementation of the 4 physical activity (PA) strategies |
September 2011-June 2012 |
Wave 1 Schools |
| Complete online school program assessment |
September-October 2011 |
Wave 1 Schools |
| Collection of Fitnessgram (FG) and PA logs |
September-November 2011 |
Wave 1 Schools |
| Submit FG and PA data to UW Population Health Institute |
October-November 2011 |
Wave 1 Schools |
| Provide PD and TA to wave 1 schools |
October 2011-May 2012 |
DPI |
| School staff and administration attend PD and seek out TA |
October 2011-May 2012 |
Wave 1 Schools
(as needed) |
| First installment of funding to project schools |
December 2011 |
DPI |
| Second collection of FG and PA logs |
April-May 2012 |
Wave 1 Schools |
| Submit FG and PA data to UW Population Health Institute |
April-June 2012 |
Wave 1 Schools |
| Complete key staff interviews |
May-June 2012 |
Wave 1 Schools |